Access at ThyssenKrupp USA Steel Processing Plant - Calvert, AL

Customer:
Contractor: LPR
Facility Owner: ThyssenKrupp USA

Spider provided access for the installation of steel girder beams on the 175 ft wide, 234 ft tall hot dip galvanizing line structure of this steel processing plant. The unique rigging solution made mobilization fast and painless and helped LPR double its crew size. 25 LPR employees completed Spider's Basic User Training and mastered the use of Spider's rigging checklist to ensure safe ongoing use of the equipment. Extensive project planning and execution to perform extremely efficient installation and relocation of equipment to minimally impact the ThyssenKrupp plant's production helped Spider drive a savings of 10 days of set up and tear down time and thousands of dollars compared with the alternative access solution considered.